Commissioners vote Tuesday on a $3.6 million deal to design a FEMA-paid repair of Ponte Vedra Beach after Hurricane Milton. It calls for 805,000 cubic yards of sand.
The next round of sand for Ponte Vedra Beach is up for a vote Tuesday. St. Johns County commissioners will consider a $3,624,521.62 contract to design, permit and oversee a FEMA-funded repair of the beach after Hurricane Milton.
The contract goes to First Line Coastal LLC. It is item 7 on the consent agenda for the Board of County Commissioners meeting at 9 a.m. Tuesday, Nov. 17, in the County Auditorium, 500 San Sebastian View, St. Augustine. Consent items pass in a single vote unless a commissioner pulls one for discussion.
What the project would do
The contract in the agenda backup says the intent is “to place 805,000 cy of sand somewhere between R25-R46.2.” The engineers and the county will decide the exact locations and the design.
R-25 and R-46.2 are the state’s beach survey markers. R-46.2 sits at the northern beach boundary of the Guana Tolomato Matanzas National Estuarine Research Reserve, according to a 2021 federal environmental review of the county’s earlier Ponte Vedra Beach project. That review counted 8.9 miles from the Duval County line at R-1 to R-46.2. The new project’s range is roughly the southern half of that stretch. The same review listed R-26 to R-31 as critically eroded.
The contract covers:
- design of the sand placement
- permits from state and federal agencies
- construction administration once work starts
The papers do not give a construction date or a construction cost. The sand itself would be placed under a separate construction contract.
Why FEMA is paying
The county rebuilt about nine miles of Ponte Vedra Beach in 2024, from the Duval County line to the Guana reserve. That $38.6 million project placed more than 2 million cubic yards of sand, the county said when it finished in July 2024. The county said then that a rebuilt beach damaged in a declared disaster could qualify for help from FEMA and the Florida Division of Emergency Management.
Hurricane Milton hit Florida three months later. The contract lists a subgrant agreement for Hurricane Milton under FEMA disaster declaration DR-4834. Category G is FEMA’s public assistance category for parks, recreational and other facilities.
The resolution says the project is funded by the county’s Disaster Recovery department and a FEMA grant. The money is already in the 2027 budget, in the county’s FEMA emergency events fund, the agenda item says.
How the firm was chosen
The county asked for qualifications May 5. Four firms responded, and an evaluation committee ranked First Line Coastal first, the agenda item says. Staff then negotiated the scope and fees.
First Line Coastal’s proposal says its team is the same one working on the county’s FEMA Category G project at South Ponte Vedra Beach. That is a separate project, south of the Guana reserve. It is also separate from the Army Corps project for South Ponte Vedra Beach that moved to design this month.
Also on Tuesday’s agenda
- Amendment 3 workshop. County Administrator Joy Andrews will brief commissioners on the expected hit to property tax revenue now that Amendment 3 has passed. The item seeks the board’s direction on keeping services running. The county has estimated a loss of $68.3 million in 2028, as our Amendment 3 story reported.
- Ponte Vedra Zoning and Adjustment Board. Consent item 16 would appoint Stephen Danner and Cecilia Birk to four-year terms ending Nov. 17, 2030.
- FPL franchise. A public hearing on a new franchise agreement with Florida Power & Light. It sets a franchise fee of 6% of FPL’s electricity revenue in the unincorporated areas the company serves, collected through customer bills.
What it means for you
- No sand yet. This contract pays for design and permits. Construction comes later, under a separate contract, and the papers give no date.
- Speak at the meeting. Public comment comes early on the agenda, before the regular items.
- Questions about the contract: the county’s Purchasing Department, 904-209-0158.